Message-ID: <19888432.1075854282701.JavaMail.evans@thyme>
Date: Mon, 1 Jan 2001 23:51:00 -0800 (PST)
From: mary.poorman@enron.com
To: daren.farmer@enron.com, gary.hanks@enron.com, edward.terry@enron.com
Subject: January Nominations at Shell Deer Park
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
X-From: Mary Poorman
X-To: Daren J Farmer, Gary A Hanks, Edward Terry
X-cc: 
X-bcc: 
X-Folder: \Darren_Farmer_Jun2001\Notes Folders\Discussion threads
X-Origin: Farmer-D
X-FileName: dfarmer.nsf

FYI - 

They did request 110M/Day, however, the load must have dropped off.  I am 
checking into this, and will email the findings.

Mary
---------------------- Forwarded by Mary Poorman/NA/Enron on 01/02/2001 07:47 
AM ---------------------------


"Shankster JL (Luther)" <JLShankster@equiva.com> on 12/19/2000 03:32:26 PM
To: "'Lamphier, Gary'" <glamphi@enron.com>
cc: "Carter, John" <JCCarter@equiva.com>, "Ricks, Ruth" <RARicks@equiva.com>, 
kyle.r.lilly@enron.com, mary.poorman@enron.com 

Subject: January Nominations at Shell Deer Park


Gary,

January 2001 nominations for gas delivery to Shell Deer Park are as follows:

Firm Baseload - 110,000 MMBtu/d
Spot Swing supply - 0 (zero)

Delivery of the above contract quantities is expected to be as follows:

  HPL-HP   HPL-E   HPL-S
 Firm 35,000 MMBtu/d 40,000 MMBtu/d 35,000 MMBtu/d

On or about January 7th we are currently planning on beginning our much
anticipated scheduled turnaround work. Natural gas demand is expected to
decrease with HPL's portion being 20,000 MMBtu/d coming primarily out of the
HP/E station. This will leave total demand at 90,000 MMBtu/d for the
remainder of the month.

Please let me know if you have any questions

J. Luther Shankster

Energy & Utilities Planning